2017年6月27日星期二

world first 1000kv AC transformer transport on road with ruiqianhe girder bridge



world first 1000kv AC transformer transport on road with ruiqianhe girder bridge

In April 27, 2017, it was an extraordinary day, because on this day, by the specific implementation of TBEA, the world's first 1000kV AC transformer analog transportation was officially completed! This is the embodiment of TBEA level promotion, and it is also the embodiment of the leap of our company's construction technology level. It's worth every one of us to be proud of!           Prior to this, ruiqianhe a series of previous experiments, through on-site meticulous cooperation, difficult construction, the transformer body smoothly transported to the designated location of analog orbit. TBEA installed the transformer accessories, and the site has all the necessary conditions for the analog transportation.           In the whole day of the simulation transport, the relevant leaders of the State Grid Company came to the scene to observe and guide, the experts of China Electric Power Research Institute to inspect, and I am responsible for organizing the construction. In the work units, the construction process smoothly, and we do pay attention to and grasp every detail, grasp the precise size, go all out to ensure that the whole simulation process is safe, stable and smooth transportation.           The successful completion of the simulated construction marks a new step in the transportation of our company.           Looking forward to the road of development in the future, we can continue to overcome new difficulties and achieve new achievements! We are also very grateful to TBEA company for its support and cooperation!

http://www.heavyhaulagetrailer.com/goldhofer-modular-trailer-multi-axle-p125.html
http://www.heavyhaulagetrailer.com/ModularTrailer.html

http://www.heavyhaulagetrailer.com/world-first-1000kv-ac-transformer-transport-on-road-with-ruiqianhe-girder-bridge.html

www.ruiqianhe.com

www.heavyhaulagetrailer.com

www.htegroup.net

www.modulartrailerchina.com
E-mail: heavytransportequipment@yahoo.com
E-mail: info@ruiqianhe.com



2017年6月21日星期三

goldhofer modular trailer 16+16 couple with girder bridge for transformer

goldhofer modular trailer 16+16 couple with girder bridge for transformer

The early morning of June 15, 2017 loaded with 400 tons of RQH girder bridge couple with goldhofer 16+16 line modular trailer carry of 1000kV transformer , so far, this project first transformer road transport mission completed successfully.           This transformer site segment transportation tasks: ship unloading loading port wharf in Tianjin, the 1000kV New River county highway transportation to Xingtai city Shijiazhuang substation, the entire 430 km or so. Although only 430 kilometers, but it is difficult 430 kilometers. Because the transformer quality is heavy, headroom, coupled with a number of road construction, part of the road transport is in the night before the rain, the entire transportation can be described as difficult ahead of the road. However, in the process of transportation, leaders at all levels to the company down to the frontline construction team to have a thought, a force to make, solidarity, teeth, efforts to overcome many difficulties, finally safely and successfully arrived at the scene, the successful completion of the transport task.
http://www.heavyhaulagetrailer.com/goldhofer-modular-trailer-multi-axle-p125.html



www.ruiqianhe.com

www.heavyhaulagetrailer.com

www.htegroup.net

www.modulartrailerchina.com
E-mail: heavytransportequipment@yahoo.com
E-mail: info@ruiqianhe.com